| | Posted by sats35 (Mr) on Aug 10 at 1:48 AM | |
Thanks Jomon..It worked..:)
josejomonm via sap-log-pm wrote:
> =09Posted by josejomonm=20
>
> on Aug 10 at 1:40 AM =09Mark this reply as helpfulMark as helpful=20
> <http://it.toolbox.com/api/ContentVote/2922750/1/1/>
>
> For Changing price of any PR line item created through IW32 / IW31=20
> please follow the following steps
> =20
> 1) Open the Order using IW32
> 2) Go to the component tab
> 3) Select the line / material for which the change to be done
> 4) click the "Purch." button at the bottom of the screen.
> 5) Change the price / qty =20
> 6) Click the "Save" button at the top of the screen
> =20
> Hope this may help you
> =20
> Regards,
> =20
> Jomon Manoj Jose
> Arabian Petrochemical Company
> +966-3-357-7417
> =20
>
> --- On Sun, 8/9/09, sats35 via sap-log-pm=20
> <sap-log-pm@Groups.ITtoolbox.com> wrote:
>
> From: sats35 via sap-log-pm <sap-log-pm@Groups.ITtoolbox.com>
> Subject: Re: [sap-log-pm] Changing Purchase Requisitions created from=20
> PM Orders
> To: "josejomonm" <josejomonm@yahoo.com>
> Date: Sunday, August 9, 2009, 8:21 PM
>
>
> Posted by sats35 (Mr)
> on Aug 9 at 11:12 PM
> Mark as helpful
> You created PR from ME51n transaction or through IW31 (where system=3D20
> internally creates a PR for non-stock item entered in components tab=20
> of =3D20
> Maintenance Order)?
> Changing PR's item price is a problem for PR generated through=3D20
> maintenance order(we cannot change even through ME52n).
> Those created from ME51n are not a problem, they can be changed=20
> through=3D20
> ME52n
> Any setup/configuration issue is preventing this?
> Rana Anwar Ali via sap-log-pm wrote:
> > =3D09Posted by Rana Anwar Ali=3D20
> > (Planning Engr./SAP PM=3D20
> > Consultant-Exp.09 Years)
> > on Aug 8 at 9:50 AM =3D09Mark this reply as helpfulMark as helpful=3D20
> > <http://it.toolbox.com/api/ContentVote/2922082/1/1/>
> >
> > Did you checked to select the Item & click on Purchasing button=20
> where=3D20
> > you can change price & other information. IN PR you can change it=3D20
> > because it is getting data from order. But text as you mentioned can=3D20
> > be editable. We are creating PR through order and working fine.
> > ________________________________
> > Rana A Ali[cid:imagebd4ce5.png@3d6bc970.f92d4d12]
> > Planning Engineer/SAP PM Power User", Maintenance Planning
> > Al-Jubail Petrochemical Company
> > A SABIC Affiliate
> > Al-Jubail 31961
> > Kingdom of Saudi Arabia
> > T +966 (3) 357 6710
> > F +966 (3) 357 6466
> > E AliAR@KEMYA.SABIC.com
> > From: sats35 via sap-log-pm [mailto:sap-log-pm@Groups.ITtoolbox.com]
> > Sent: Saturday, August 08, 2009 2:07 PM
> > To: Ali ,Rana Anwar
> > Subject: [sap-log-pm] Changing Purchase Requisitions created from PM=3D20
> > Orders
> > [http://userimages.toolbox.com/user/b_1448234.jpg]
> > Posted by sats35 (Mr)
> > on Aug 8 at 9:20 AM
> > We create maintenance order (iw31) and in components tab, we give=3D20
> > material codes that needs to be procured with item category as 'N'=3D20
> > (non-stock) so that PR gets generated. The issue currently we have=20
> is,=3D20
> > PR created this way is not editable except for some free text=20
> fields,=3D20
> > even though we open the PR with ME52n.For ex: Valuation Price in=3D20
> > Valuation tab(esp if we know, that current market price is either=3D20
> > considerably high or low from the one defaulted from material=20
> master),=3D20
> > delivery_date (we found a work around the change basic start date in=3D20
> > maintenance order to delivery date). Is there some setting we should=3D20
> > do in SPRO to see that PR opens up for editing (just the way a PR=3D20
> > created through ME51n).
> > This is a burning problem as Purchase are not willing to enter=3D20
> > considerable higher or lower price (than that in PR) while=20
> maintaining=3D20
> > RFQ(ME47).
> > -Thanks in advance
> > Satish
__.____._ josejomonm via sap-log-pm wrote:
> =09Posted by josejomonm=20
>
> on Aug 10 at 1:40 AM =09Mark this reply as helpfulMark as helpful=20
> <http://it.toolbox.com/api/ContentVote/2922750/1/1/>
>
> For Changing price of any PR line item created through IW32 / IW31=20
> please follow the following steps
> =20
> 1) Open the Order using IW32
> 2) Go to the component tab
> 3) Select the line / material for which the change to be done
> 4) click the "Purch." button at the bottom of the screen.
> 5) Change the price / qty =20
> 6) Click the "Save" button at the top of the screen
> =20
> Hope this may help you
> =20
> Regards,
> =20
> Jomon Manoj Jose
> Arabian Petrochemical Company
> +966-3-357-7417
> =20
>
> --- On Sun, 8/9/09, sats35 via sap-log-pm=20
> <sap-log-pm@Groups.ITtoolbox.com> wrote:
>
> From: sats35 via sap-log-pm <sap-log-pm@Groups.ITtoolbox.com>
> Subject: Re: [sap-log-pm] Changing Purchase Requisitions created from=20
> PM Orders
> To: "josejomonm" <josejomonm@yahoo.com>
> Date: Sunday, August 9, 2009, 8:21 PM
>
>
> Posted by sats35 (Mr)
> on Aug 9 at 11:12 PM
> Mark as helpful
> You created PR from ME51n transaction or through IW31 (where system=3D20
> internally creates a PR for non-stock item entered in components tab=20
> of =3D20
> Maintenance Order)?
> Changing PR's item price is a problem for PR generated through=3D20
> maintenance order(we cannot change even through ME52n).
> Those created from ME51n are not a problem, they can be changed=20
> through=3D20
> ME52n
> Any setup/configuration issue is preventing this?
> Rana Anwar Ali via sap-log-pm wrote:
> > =3D09Posted by Rana Anwar Ali=3D20
> > (Planning Engr./SAP PM=3D20
> > Consultant-Exp.09 Years)
> > on Aug 8 at 9:50 AM =3D09Mark this reply as helpfulMark as helpful=3D20
> > <http://it.toolbox.com/api/ContentVote/2922082/1/1/>
> >
> > Did you checked to select the Item & click on Purchasing button=20
> where=3D20
> > you can change price & other information. IN PR you can change it=3D20
> > because it is getting data from order. But text as you mentioned can=3D20
> > be editable. We are creating PR through order and working fine.
> > ________________________________
> > Rana A Ali[cid:imagebd4ce5.png@3d6bc970.f92d4d12]
> > Planning Engineer/SAP PM Power User", Maintenance Planning
> > Al-Jubail Petrochemical Company
> > A SABIC Affiliate
> > Al-Jubail 31961
> > Kingdom of Saudi Arabia
> > T +966 (3) 357 6710
> > F +966 (3) 357 6466
> > E AliAR@KEMYA.SABIC.com
> > From: sats35 via sap-log-pm [mailto:sap-log-pm@Groups.ITtoolbox.com]
> > Sent: Saturday, August 08, 2009 2:07 PM
> > To: Ali ,Rana Anwar
> > Subject: [sap-log-pm] Changing Purchase Requisitions created from PM=3D20
> > Orders
> > [http://userimages.toolbox.com/user/b_1448234.jpg]
> > Posted by sats35 (Mr)
> > on Aug 8 at 9:20 AM
> > We create maintenance order (iw31) and in components tab, we give=3D20
> > material codes that needs to be procured with item category as 'N'=3D20
> > (non-stock) so that PR gets generated. The issue currently we have=20
> is,=3D20
> > PR created this way is not editable except for some free text=20
> fields,=3D20
> > even though we open the PR with ME52n.For ex: Valuation Price in=3D20
> > Valuation tab(esp if we know, that current market price is either=3D20
> > considerably high or low from the one defaulted from material=20
> master),=3D20
> > delivery_date (we found a work around the change basic start date in=3D20
> > maintenance order to delivery date). Is there some setting we should=3D20
> > do in SPRO to see that PR opens up for editing (just the way a PR=3D20
> > created through ME51n).
> > This is a burning problem as Purchase are not willing to enter=3D20
> > considerable higher or lower price (than that in PR) while=20
> maintaining=3D20
> > RFQ(ME47).
> > -Thanks in advance
> > Satish
Copyright © 2009 CEB Toolbox, Inc. and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
White Papers
In the Spotlight
SAP Enterprise Software: flexible, best-of-breed business apps View Vendor Profile
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion