Re: [sap-log-pp] Re-Exploding of BOM at the time of planned order to production order conversion
Posted by
Admin at
|
Share this post:
|
on 06/18/2009 01:11:00 AM
Thanks a lot Bob and Sandy,
I would prefer MD12 as the solution.
Thanks a lot again
regards
charith
On Wed, Jun 17, 2009 at 6:16 PM, sandy via sap-log-pp <
sap-log-pp@groups.ittoolbox.com> wrote:
>
>
>
> hi Charith,
> At the time of conversion from planned order to production order system is
> copying the current bom into production order(please check the bom change
> date).
> e.g
> mrp date: 01.06.2009
> planned orders:
> 05.06.2009 50qty
> 10.06.2009 50qty
> You changed bom on 08.06.2009
> 1) if you convert first planned order(05.06) the change will not reflect in
> prod order for this u can use Read PP master data function.
> 2) for prod order conversion after 08.06.09(i.e planned order 10.06) date
> your current bom will get copy so u will see components as per tht.
>
> Date: Wed, 17 Jun 2009 16:52:55 +0530
> Subject: [sap-log-pp] Re-Exploding of BOM at the time of planned order to
> production order conversion
> From: sap-log-pp@Groups.ITtoolbox.com
> To: siddhesh103@hotmail.com
>
>
> Toolbox sap-log-pp
>
> Hi All,
> Is there anyway to re-explode the BOM at the time of conversion of planned
> order to Production order.
> We dont have APO with us ....
> At the time of the conversion, the changes done after the last MRP run
> should get through BOM explosion at the time of conversion of planned order
>
> to production order, this is the customer requirment.
> Pls advice me if there is any possiblity. thanks a lot in advance
> Regards
> Charith __.____._
Toolbox.com
4343 N. Scottsdale Road
Suite 280
Scottsdale, AZ 85251
In the Spotlight
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion