Question from bybarsse on Nov 5 at 8:54 PM We are running a pure Customizing house where Project Systems and WBS are activated. I know for a project A all work centers dates where the subassembly should transit. However, I do not have visibility on the complete subassembly BOM because the MPS is always late. So I need to create PIR for main components. For example: For a project A the subassembly B will transit in the work center Z at the date T. I want to create separately a PIR for a major components C who will be used in B. And need that my Planned dates for C be linked to the work center Z dates (T) so my dates will follow the WC dates in case they change in the future (the MS is always changing) Is there any way to do that in SAP? Regards | Reply to this email to post your response. __.____._ | _.____.__ |