RE: [sap-log-pp] How to Convert a Finished Material to Unfinished Material After Jobwork Found Rejected

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from giso_vonpetersdorff on May 1 at 5:04 AM
Hello Anonymous

There is no need to do any configuration. Assuming that you are using production orders for your manufacturing, create a new order for the finished product that needs to be reworked, with the quantity of the defect items. Go to the component list, enter the finished material number as a component and delete all the components that are not needed. You can also change the operation(s) as needed on the order. The same procedure can be followed for process orders.
Regards
Giso

---------------Original Message---------------
From: guest
Sent: Friday, May 01, 2015 2:52 AM
Subject: How to Convert a Finished Material to Unfinished Material After Jobwork Found Rejected

After the job work done, we found the finished material got rejected in the quality assurance, then how to convert that finished material into unfinished material? What are the configuration steps or procedure such scenarios?

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2015 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
giso_vonpetersdorff  

achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language