Reply from Empic on Feb 20 at 1:57 AM Try to run MD03 or MD02 for your material. If you have need for your material (sales order, reservations, etc.....) and 0 stock and if nothing happened, you must go through customizing and check if MRP is active for your plants. And go through all customizing in SPRO->Materials management-> Consumption based planning Good luck
| | | ---------------Original Message--------------- From: Mark Summerbell Sent: Thursday, February 19, 2015 11:04 AM Subject: Setting up MD04 Hi All, My company does not actively use MRP to plan production runs and order raw materials; but we have recently acquired another plant that in the past used MD04 screen to see orders and deliveries. I must admit, this is a very useful screen. I have completed a small amount of config in SALES > BASIC FUNCTIONS > AVAILABILITY CHECK AND TRANSFER REQUIRMENTS > TRANSFER REQUIRMENTS > DETERMINATIONS OF REQ TYPES USING TRANSACTIONS. I have found what item category we use and entered 041 (Orders and deliveries)against this. I have then marked one of the materials as: PD MRP Type Lot Size EX lot for lot But still nothing appears in MD04. Can anyone give me any pointers here? Is there more config needed? We do not actually want to execute MRP we only want to use MD04 for stock displays / orders displays / delivery display. I have marked the item catergopry for orders/deliveries in SPRO and created a new order but still nothing in MD04, I have also marked the material master as PD MRP but we are still keeping the availability check marked as KP on the material master. Thanks, Mark. | | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |