Reply from bibhuranjanhota on Feb 25 at 9:20 AM Once the accounts are finalized and audited like Base year 2012, 2013. It is never be advisable to open the period and settle the orders. Any deviation will hit to Price variance a/c & it will be part of consumption only.
| | | ---------------Original Message--------------- From: pradeep khairnar Sent: Wednesday, February 25, 2015 2:30 AM Subject: Settlement by IW32 Tcode Hi, It is correct that once the goods issued to Maintenance order or receipt the external services for the Order the accounting documents were updated in FI. Now as a part of Monthly/Quarterly/Yearly The settlement of cost for the Internal Order should be done in proper manner. NO P/L impact on settlement of Order. This will be enhance to the planner correct picture of cost for the respected CC and helps to allocate/revised the budget for the maint. activities in Plant. K PRADEEP | | Reply to this email to post your response. __.____._ | _.____.__ |