RE:[sap-log-pp] Production Completion Date Vs. Load Date

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from brsdiehard on Dec 25 at 2:12 PM
You use the Schedule Margin Key using the float after production. For example, if you enter 5 day float after production, the scheduled production completion date will 1/5/15 and the production order finish date will be 5 days later or 1/10/15.

---------------Original Message---------------
From: Michelle
Sent: Wednesday, December 17, 2014 10:21 AM
Subject: Production Completion Date Vs. Load Date

This question may actually be a mix of production planning and sales order entry.

We need time after production for crating, or waiting for customer instructions on ship via. We keep looking like we are shipping orders late, however our production is completed on time.
how can we have a variable gap between production completion and load date?

Thank you

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2014 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
brsdiehard  

achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have a technical question? Need to find IT solutions? Ask your peers in the Toolbox for IT community.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language