Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Reply from TMcGinn on Sep 23 at 10:01 PM Thanks Paul this sounds like it will work! I will try it now. Thanks again
| | | ---------------Original Message--------------- From: pauljb470 Sent: Tuesday, September 23, 2014 7:48 PM Subject: How can adjust the call horizon on a PM plan to 200% in SAP PM? tom, if you are unable to activate the enhancement you can adjust the 'interval for call objects' in your ip30 job It will force the job to look ahead and call orders earlier. In your case, you could leave your plan as is. Make the interval 7 days and it will generate orders a further 7 days in advance of when they would normally be due. You will end up with as many weeklies into the future as you like. 14 day would make it 14 days in advance, etc. (As long as your plan isn't marked for completion requirement) | | Reply to this email to post your response. __.____._ | _.____.__ |