Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Question from rsteinbe on Aug 28 at 8:53 AM Hello, We are settling by cost element from orders to network activities. Beside, there are confirmations directly on the network activity. While executing CN41n / CNS41 / CN41 or similar structure reports just the hours from the confirmation are shown in the column actual work. Somehow just AFVV is read while executing even when in table RPSQT the correct values including the settlement quantities are available. How can I show both values in column actual work? Any help is appreciated. Best wishes Rog | Reply to this email to post your response. __.____._ | _.____.__ |