Question from pankaj83 on Aug 31 at 12:50 PM Hi All I have dunning at 30,45,60,75 days 1) I posted with FB70 with baseline date 30 days behind posting date i.e. if posting date is 30th Aug then baseline date as 29th July. This made it overdue. 2) I ran dunning through F150 and dunning was done with all print out & customer showing dunning level as 1. My question is how to run dunning level 2? Please advice in steps. Regards Pankaj | Reply to this email to post your response. __.____._ | _.____.__ |