Reply from quest on Aug 25 at 1:07 AM Hi Eric, thank you for suggestion but we have to keep MRP controller as it is. Also thank you Bob, but exception is not welcomed and automatically update of planned order is needed.
| | | ---------------Original Message--------------- From: quest Sent: Friday, August 22, 2014 3:23 AM Subject: Individual Settings for Planned Order Hello, Is it possible to individually change planned order (f.e. GR processing time) and keep this setting the way that planned order will be not fixed? I have tried changed order = automatically fixed / then I have removed fixed indicator but when MRP runs the order is automatically deleted. We need to have first planned order planned with different conditions than the other planned orders. But the order must respect MRP. Micha | | Reply to this email to post your response. __.____._ | _.____.__ |