Reply from chanshekgan on Mar 11 at 7:50 AM Thanks Sir for the quick tip Chandrashekar
| | | ---------------Original Message--------------- From: Nat Govender Sent: Monday, March 10, 2014 12:26 AM Subject: Edit Cost Ccenter on SES Final Release Hi, I am assuming that SES refers to Service Entry Sheet. To answer your question from my understand you cannot. From my understand SES does not have the accounting details, this can be found on the PO. Even if you change the Cost Centre on the PO this would not help because the account entry for the SE after released was already done. You would first need to reversed and delete the original SES then change the CC on the PO and then create a new SES. Kind regards, Nat Govender | IT Specialist : SAP Workflow | | | Reply to this email to post your response. __.____._ | _.____.__ |