Reply from fakirmohan_bagar on Mar 11 at 7:32 AM Dear Karthick, Yes, you can set warning / error as per your requirement to block over confirmation of second process than first operation. In OPk4, move to "Parameter for Order Confirmation" screen. Change "Operation Sequence" as per the requirement. Regards, Fakir Mohan Bagar Manager - ICT
| | | ---------------Original Message--------------- From: karthick Sent: Tuesday, March 11, 2014 7:16 AM Subject: Routing Operation Confirmation Dear All, I was new to PP... I was in testing phase for operation based order confirmation. Is that possible to block the over confirmation of second process than first operation? Or should Warn the confirmation and should post in COGI... Customization should be done or what can I do??? | | Reply to this email to post your response. __.____._ | _.____.__ |