RE:[sap-bw] How to Run the Process Chain First 8 Working Days

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from Vikranth on Feb 5 at 12:42 AM
Hi Subhash,

I have two options for you.

Please try the below two things at the starting of your Process chain after the Start Variant,

1) Decision between Multiple alternatives:

See, if you have any formuala / Condition where you can use like, if First 8 WDs - then true (1) else False (2).

In this case, if it can recognize the first 8 days then it will pass through 1st option, else it will go through 2nd option and get finished.

2) ABAP Program / ABAP Program with Status:

Write an ABAP code, which will read System date/month/year. When the Program recognizes the first 8 days of month, then it will run further. Else, keep a dummy step which ends if condition is not true.

Hope this helps.

Let me know if you are looking for more info.

Thanks,
Vikranth.

---------------Original Message---------------
From: sapbwfaq224
Sent: Tuesday, February 04, 2014 10:22 PM
Subject: How to Run the Process Chain First 8 Working Days

Hi,

My requirement is

How to run the process chain first 8 working days of every month.

Can anyone recommend how to fulfill this requirement?
And where I have to write in process chains?

Thank you,
Subhash.

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2014 Ziff Davis, Inc. and message author.
Ziff Davis, Inc. 28 E 28th Street New York, NY 10016
Vikranth  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have a technical question? Need to find IT solutions? Ask your peers in the Toolbox for IT community.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language