Re: [sap-log-mm] Week Wise Schedule Line Generation Wants Through MRP

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from ssundarsarangan on Feb 9 at 8:28 PM
Hello

Use OMUP Release creation profile. Customize the bucket as you want weekly, monthly, and daily basis
and attach this profile in you schedule agreement in the Item level.

With Regards
S.Sundar

---------------Original Message---------------
From: sop57
Sent: Sunday, February 09, 2014 8:06 PM
Subject: Week Wise Schedule Line Generation Wants Through MRP

Hi,
Two ways to do this - presuming you are not using APO!!
1 On the MRP1 screen set the MRP type to WB (Weekly batches)
OR better still
2 Create a vendor calendar (transaction MD25)which has one entry for each week. The advantage of using Vendor Calendars is that you can remove any weeks when the vendor has a shutdown, so MRP will plan for the supply of material to cover the shutdown to be available before the vendor holiday. Once you have created the calendar, it is entered on the MRP2 screen in the Planning Calendar field. You also need to change the MRP type to whichever one has been set up in your system to use the planning calendar.
Regards,
SOP57

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2014 Ziff Davis, Inc. and message author.
Ziff Davis, Inc. 28 E 28th Street New York, NY 10016
ssundarsarangan  
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Have a technical question? Need to find IT solutions? Ask your peers in the Toolbox for IT community.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language