Reply from VEDHEREV on Feb 1 at 9:57 PM Assign plant 1000 to porg 1100 ALSO and then check. Also check the assignments in entire org structure from company code to plant.
| | | ---------------Original Message--------------- From: Ranjjini SG Sent: Saturday, February 01, 2014 8:49 PM Subject: Error during PO Creation While Referring Purchase Organisation Contract Hi all, I m facing issue with the following scenario. 1. Purchase organisation 1100 is assigned as reference purchase org for P.org 1000 2. Created contract with for P.org 1100 3. Plant 1000 is assigned to P.org 1000. Now i m trying to create PO for plant 1000 referring contract of P.org 1100. system automatically copies P.org 1100 into PO document 4. on save system throws following error "p.org 1100 not responsible for plant 1000" Kindly help Thanks in advance Ranjjini | | Reply to this email to post your response. __.____._ | _.____.__ |