AW: [sap-bw] How to Run the Process Chain First 8 Working Days

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from sviszt on Feb 5 at 3:10 AM
Hi,

If you want a ?cheap" solution without programming, simply schedule the process chain for the first 8 days. You can go to "Scheduled jobs?" in the context menu of the start process and copy the job 7 times.

To implement your own decision process type:
? Create a new class in se24
? Implement at least the following interfaces: IF_RSPC_EXECUTE, IF_RSPC_MULTI_EVENT
? In RSPC diplay a process chain.
? Under settings select maintain process types
? Create a new entry specifying your class and the proper settings
? Use the process in your process chain
This way you can implement almost any functionality.

Oliver

---------------Original Message---------------
From: sapbwfaq224
Sent: Tuesday, February 04, 2014 10:22 PM
Subject: How to Run the Process Chain First 8 Working Days

Hi,

My requirement is

How to run the process chain first 8 working days of every month.

Can anyone recommend how to fulfill this requirement?
And where I have to write in process chains?

Thank you,
Subhash.

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2014 Ziff Davis, Inc. and message author.
Ziff Davis, Inc. 28 E 28th Street New York, NY 10016
sviszt  

achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Become a blogger at Toolbox.com and share your expertise with the community. Start today.

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language