Reply from R. N. Wilhite on Jan 28 at 1:00 PM Can you manually change the dates of a locked wbs? If not, the BAPI should not let you do it either. If these are the case, the proper method would be test for lock, unlock, change dates, lock. I agree that the popup is wrong. If you have a real problem with it, then I suggest that you write a problem message to OSS. Neal
| | | ---------------Original Message--------------- From: Alexandra Sent: Monday, January 28, 2013 11:38 AM Subject: Message CJ175 Appears As Pop Up in BAPI_PROJECT_MAINTAIN Hello, I have a problem using the BAPI_PROJECT_MAINTAIN for updating WBS-Dates. More precisely, I try to modify the dates for a WBS Element which has the status LKD (Locked). The information message which I receive is correct (CJ175 - " The dates for WBS Element & cannot be changed"). It is wrong that I receive a POP UP screen while executing the BAPI instead of seeing the message in the table that the bapi returns. I have checked for SAP Notes, but I have found none for this message issued by FM "CJDT_PRTE_MODIFY', called within the bapi. Has anyone had the same problem and found a solution for it? Thank you, Alexandra | | Reply to this email to post your response. __.____._ | _.____.__ |