Question from vijesh-vijayan on May 7 at 1:24 AM Hi all, In our scenario we are souring packing from suppliers. The lead time for the packaging is differs ,i.e., if it is new item the lead time is 4 weeks and for the old one the lead time is 3 weeks. For the new items we can update the lead time as 4 weeks once the item is received can system change it the lead time to 3 weeks automatically? Can SAP do it? Please advise. Regards, | Reply to this email to post your response. __.____._ | _.____.__ |