Reply from ha_tran on May 27 at 7:58 PM Hi Abhi, The delivery date in the purchase requistion is calculated from the planned delivery time setting in either material master or purchasing master data such as info record. If no material master is used, then today's date is defaulted. Cheers, HT
| | | ---------------Original Message--------------- From: abhijeet naik Sent: Saturday, May 26, 2012 9:30 AM Subject: Planned Delivery Dates in PO SAP MM where the planned delivery dates in PO comes from? In case of of no material number where this plan delivery dates comes from? If need to take planned delivery date from Contract, what setting you need to do? need to know the role of source list, Purchase inforecord & material master setting affects the planned delivery date of Purchase order. Awaiting reply. Best Regards Abhi | | Reply to this email to post your response. __.____._ | _.____.__ |