In case if you assigned new work schedule to an ee it reads one day old w s ,ensure you generated old work schedule rule. Manoj WIPRO
| | | ---------------Original Message--------------- From: Manoj Gupta Sent: Monday, December 13, 2010 12:06 AM Subject: Time Evaluation Error Hi Raj, Please check WSR has been generated from the day retro calc is set. This is the problem comes either due to wrong configuration of WSR or WSR is not generated for the period TE starts and runs upto. Good luck. Manoj | | __.____._ Copyright © 2010 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Most Popular White Papers In the Spotlight _.____.__ |