Posted by a_godfrey (Independent Contractor) on May 22 at 7:30 PM | Mark as helpful |
This sounds to me that you have not set the internal orders to automatically activate availability control on the budget being entered.
To do this, in the budget profile, you need to set Activation Type to 1.
For any existing internal orders with budgets that you want to have availability control active, use transaction KO30.
Hope this helps
?
Allan Godfrey
>A.P. Godfrey Consulting Inc.
>http://www.linkedin.com/in/allangodfrey
>P?Please consider the environment before printing this e-mail and any documents
________________________________
From: JOMLV via sap-acct <sap-acct@Groups.ITtoolbox.com>
To: a_godfrey <allan_godfrey@rogers.com>
Sent: Sat, May 22, 2010 4:46:49 PM
Subject: [sap-acct] Availability check on internal orders
Posted by JOMLV (Project Manager)
on May 22 at 4:45 PM
Dear All,
I have an issue on availability check (AVAC) with internal orders. yet Committment management in CO is activated, as comittment in the order type. I also defined tolerance limits for AVC, for group all, ++, action 3 :error at 105 %.
Then the internal order is budgeted by the users, but when they add purchase orders (committments) or make reception on that PO with an amount that is more than the budget, no message at all is raized.
Everything sounds OK, in KO23 when analysing the AVAC log, all is active, operations from BS32, COIN ,RMBE, (commitmment : PO requets and Request) are done, but no operatin for Budget :RXPA.
In order to replay the tests, do you know how to budget an internal order ? Is there additionnal customizing to do for AVAC, in MM on the Purchase Orders side maybe ?
Jean,
__.____._ To do this, in the budget profile, you need to set Activation Type to 1.
For any existing internal orders with budgets that you want to have availability control active, use transaction KO30.
Hope this helps
?
Allan Godfrey
>A.P. Godfrey Consulting Inc.
>http://www.linkedin.com/in/allangodfrey
>P?Please consider the environment before printing this e-mail and any documents
________________________________
From: JOMLV via sap-acct <sap-acct@Groups.ITtoolbox.com>
To: a_godfrey <allan_godfrey@rogers.com>
Sent: Sat, May 22, 2010 4:46:49 PM
Subject: [sap-acct] Availability check on internal orders
Posted by JOMLV (Project Manager)
on May 22 at 4:45 PM
Dear All,
I have an issue on availability check (AVAC) with internal orders. yet Committment management in CO is activated, as comittment in the order type. I also defined tolerance limits for AVC, for group all, ++, action 3 :error at 105 %.
Then the internal order is budgeted by the users, but when they add purchase orders (committments) or make reception on that PO with an amount that is more than the budget, no message at all is raized.
Everything sounds OK, in KO23 when analysing the AVAC log, all is active, operations from BS32, COIN ,RMBE, (commitmment : PO requets and Request) are done, but no operatin for Budget :RXPA.
In order to replay the tests, do you know how to budget an internal order ? Is there additionnal customizing to do for AVAC, in MM on the Purchase Orders side maybe ?
Jean,
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
_.____.__ White Papers
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements