| Posted by gupta-rajeev (mm) on May 22 at 8:41 PM | |
ZReport is a client report it is not a standard report
Sent from Havells Blackberry Services
----- Original Message -----
From: "sop57 via sap-log-mm" [sap-log-mm@Groups.ITtoolbox.com]
Sent: 05/22/2010 06:05 PM AST
To: Rajeev Gupta
Subject: RE:[sap-log-mm] Report to see PO Change History
Uuse google to search for report ZPOCHANGE and import it into your system. It is very useful - we have used it for years.
Regards,
SOP57
---------------Original Message---------------
From: jaya.yanto
Sent: Friday, May 14, 2010 4:02 AM
Subject: Report to see PO Change History
> Dear Experts,
>
> I have a requirement to have a report to see PO Change History (esp. Delivery Date).
>
> Our operation is facing problems with the vendors' delayed deliveries.
> Hence, our management would like to implement penalty system for these delays.
> At the moment, our current practice is to update the Delivery Date in the Line Item whenever our vendor informs us on any delay in deliveries. This change is then reflected in the Item Changes record.
>
> Is there any standard SAP report that I may use ?
>
> Any advice and opinion is very appreciated.
>
> Thank you very much,
>
> Jaya (Singapore)
.
__.____._ Sent from Havells Blackberry Services
----- Original Message -----
From: "sop57 via sap-log-mm" [sap-log-mm@Groups.ITtoolbox.com]
Sent: 05/22/2010 06:05 PM AST
To: Rajeev Gupta
Subject: RE:[sap-log-mm] Report to see PO Change History
Uuse google to search for report ZPOCHANGE and import it into your system. It is very useful - we have used it for years.
Regards,
SOP57
---------------Original Message---------------
From: jaya.yanto
Sent: Friday, May 14, 2010 4:02 AM
Subject: Report to see PO Change History
> Dear Experts,
>
> I have a requirement to have a report to see PO Change History (esp. Delivery Date).
>
> Our operation is facing problems with the vendors' delayed deliveries.
> Hence, our management would like to implement penalty system for these delays.
> At the moment, our current practice is to update the Delivery Date in the Line Item whenever our vendor informs us on any delay in deliveries. This change is then reflected in the Item Changes record.
>
> Is there any standard SAP report that I may use ?
>
> Any advice and opinion is very appreciated.
>
> Thank you very much,
>
> Jaya (Singapore)
.
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Related Content
In the Spotlight
White Papers
In the Spotlight
Your SAP Security is at Risk...Learn How to Stay Protected. Read the free white paper from SenSage
View this thread online
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion
Manage group e-mails
Create an FAQ on this topic
Tell us what you think
Unsubscribe from discussion