Question from rrojo on Nov 10 at 4:11 AM To clarify. Is it correct to start a refurbishment work order on a part that came off a refurbishment Work order? I started the refurbishment process on a equipment and have order parts. Our inventory count is correct the parts did come out of inventory and were assigned to the refurbishment work order. However, there is a shaft that was replace and it is repairable. The shaft was also a part I got from inventory. Am I correct to use the same refurbishment work order (pm04) to create another PM04 work order so I can get it fix. Any help will do. Thank you very much!! | Reply to this email to post your response. __.____._ | _.____.__ |