Reply from guest on Oct 21 at 8:45 AM In addition to setting the MRP job to complete by 6 AM (we run all product in one job), the planner has the option to use MD02 to run for a specific material if changes in demand or other occurs after your job for MRP update.
| | | ---------------Original Message--------------- From: Vlad Selsky Sent: Wednesday, October 19, 2016 3:18 PM Subject: Multiple MRP runs for same plant It appears that SAP does not allow MRP to run concurrently for same plant. This is quite surprising. I have an MRP run for raw materials scheduled at 4 am that takes a few hours. I also have another MRP job that needs to run as close as possible to 6 am for same plant. That first job often runs long and the second job aborts. I shouldn't be forced to have to reschedule either job. Anybody have solutions or further perspectives on this? Thanks, Vlad | | Reply to this email to post your response. __.____._ | _.____.__ |