RE:[sap-log-mm] What is the Difference Between PDT (Planned Delivery Time) & TRLT (Total Replenishment Lead Time) in SAP (Fields Are in Material Master)

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from sop57 on Mar 2 at 4:38 PM
HI,
TRLT for a purchased part, as well as the supplier's lead time, also includes your internal processing time - the frequency of running MRP (which could be the time between the requirement existing up to the next run of MRP which produces the PR), plus the time it takes for you to have the purchase requisition authorised, the time to convert it into a PO and the time to deliver the PO to the supplier.
Regards,
SOP57

---------------Original Message---------------
From: Ricck
Sent: Friday, February 12, 2016 8:40 PM
Subject: What is the Difference Between PDT (Planned Delivery Time) & TRLT (Total Replenishment Lead Time) in SAP (Fields Are in Material Master)

I have been told that PDT is a field used only for "supplier lead time" and is hard coded to only be calendar days as compared to TRLT which is for lead time to customers, and the field is hard coded to be in working days.

I am aware that TRLT contains transit time which is added to PDT. Just want to confirm if the type of days (working or calendar) are hard coded and if the use if flexible (determined by the company using the SAP ERP).

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
© 2016 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
sop57  

achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language