Question from Talha38 on Feb 19 at 12:21 AM At initial stages Cost Estimate for a material 111 was released with no BOM. But when BOM was created with all master data for production, cost estimate can not be released again. It need to be re-organized by CKR1. There is a case that one component of material BOM of 111 was previously used for production in BOM of material 222. Can anybody tell me what will be the impact when re-organizing cost estimate and then release for material 111 with its BOM? | Reply to this email to post your response. __.____._ | _.____.__ |