Reply from deomb on Feb 26 at 11:54 PM I think you mean availability control per Cost Element? The SAP Availability Control checks only on total expenditure, not per Cost Element. You can however define Value Categories and assign Cost Elements to Value Categories (transaction OP11). In this way you can monitor(on PS Cost Reports) on Value Category level (=Cost Element Level). Use transaction CJR2 to plan cost per Cost Element.
| | | ---------------Original Message--------------- From: Kamini Desai Sent: Wednesday, January 14, 2015 12:38 PM Subject: Soft Error When There is No Budget On the Specific WBS ELEMENT and the COST ELEMENT. Hi, I was wondering is there any way we can get the soft error when there is no budget on the specific WBS ELEMENT and the COST ELEMENT. | | Reply to this email to post your response. __.____._ | _.____.__ |