Reply from amardhawade on Feb 4 at 12:28 AM Hi, The cost center is picked in MIRO from PO. So you need to assign the cost center while making the PO itself. You can change it every PO. Hope this solves your problem. Amar
| | | ---------------Original Message--------------- From: tapasbarik Sent: Wednesday, February 04, 2015 12:13 AM Subject: Cost Centre Picking During MIRO Dear Sridhar, Can you please explain more about substitution for my case? I have only one business area say 0001 and three cost centers say X Y & Z for three mines say A B & C within the same BA. Now my requirement is during MIRO system should pick CC X for mines A, CC Y for mines B and CC Z for mines C without defaulting in CC in cost element. TK | | Reply to this email to post your response. __.____._ | _.____.__ |