Reply from pynksox on Jan 19 at 3:21 PM Be sure your planning calendar is set up correctly.
| | | ---------------Original Message--------------- From: Me-Ann Garra Sent: Friday, January 16, 2015 11:52 AM Subject: Planned Delivery Date in Working Day We want to set-up for our externally procured materials that planned delivery date should only be every Thursday of each week. We already configured for factory Z1 and value is 4 (which is Thu) and correspondingly assigned the said fac cal in the MRP View. However, the delivery dates in the planned orders are not falling on every Thursday. Any missing configure or set-up or wrongly configured/set-up? | | Reply to this email to post your response. __.____._ | _.____.__ |