Reply from Alarias on Dec 18 at 1:43 AM Have you run previously CNE1? It is needed to get results in CNE5
| | | ---------------Original Message--------------- From: USER_2585666 Sent: Monday, December 08, 2014 12:30 AM Subject: BCWS and BCWP Not Getting Calculated Properly Dear All, BCWS and BCWP is not getting calculated: Activities created and work has been assigned. Measurement Method selected is "Cost Proportional". in Report CNE5, BCWS and BCWP values are shown as zero. The work unit (example: AU, TO, Kg etc) assigned for an external activity alone is appearing in the CNE5 report, but not showing the values. Is there any IMG setting need to be changed for getting the value of BCWS and BCWP? Whether the BCWS and BCWP will work only for External Activity? Regards, M.Rajasundaram | | Reply to this email to post your response. __.____._ | _.____.__ |