Reply from Ramakrishnan on Sep 22 at 2:23 AM Hi, I believe it is not possible in SAP to change the validity period to the prior date. Regards, Ramakrishnan. S
| | | ---------------Original Message--------------- From: KAD Sent: Sunday, September 21, 2014 12:18 PM Subject: Change Date of Validity for Cost Center Hi We are implementing HR module in our system which has already FI/CO implemented since 2003, the problem is when inserting (by LSMW) the historic of hiring process an error occur because of date of validity for Cost Center which start at 01.01.2003. My question : Is there any way to modify the period of validity of CC & PC to make it start at 01.01.1950 for all Cost Center and by consequence for all Profit Center too? What is the impact in FI/CO module of such change in validity period of CC & PC? Thanks in advance. Kaddafi BRAHIM | | Reply to this email to post your response. __.____._ | _.____.__ |