Reply from USER_2585666 on Jul 28 at 2:32 AM Project A--in Project builder-->select finishing activity no > Relation ship overview (link symbol) ==> successor tap-->Pls link the project B starting Network & activity no, Ensure that after changes made pls made scheduling action in A project, then made B project. Please try it. Hope will work. Regards, M.Rajasundaram
| | | ---------------Original Message--------------- From: wnash7658 Sent: Sunday, July 27, 2014 12:24 PM Subject: Project Scheduling With Activities Across Multiple Project Not as big PS consultant, but wouldn't this be under one project? Regards Waza | | Reply to this email to post your response. __.____._ | _.____.__ |