Reply from Hamed_Abedi on Jun 15 at 6:44 AM Dear Shoaib, Thanks for your reply. In fact, as you said, the problem was in MRP4 tab of Material Master. I changed BOM Exp./Dep. Req. to "individual" and the problem is solved. Though, I am not sure about other impacts this change might have. Regards, (Hamed)
| | | ---------------Original Message--------------- From: Hamed_Abedi Sent: Saturday, June 14, 2014 6:52 AM Subject: Reservation not shown for Project Material We have entered some semi-finished materials under an activity in a project, but no reservation shown for them in MD04. For other finished materials, under the same activity, there is no problem. Note: below Proc.Parameters are not set for semi-finished items, though we cannot change/set them in PS: -Acct.assig.cat -Special Stock -Valuation -Consumption Can anyone please help with this issue? Thanks, | | Reply to this email to post your response. __.____._ | _.____.__ |