[sap-log-pp] BAPI_PLANNEDORDER_CHANGE Generates Wrong Start Date

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Question from CWKorn on Apr 25 at 12:55 PM
When I use MD12 (Change Planned Order) to blank out the Order Finish Date and the Planned Opening Date and enter a new Start Date, I get an updated planned order with the Start Date that I entered. When I use function BAPI_PLANNEDORDER_CHANGE to do the same thing (blank out the Finish and Planned Opening Dates and enter a new Start Date) I get a Start Date that is about six weeks later than the date I entered.
When I use the function to change the Finish Date on a planned order, I get the finish date I entered -- my problem only seems to occur with the Start Date.
Does anyone have experience getting this function to update the planned start date correctly? Thanks for you help.
Carl
 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2014 Ziff Davis, LLC. and message author.
Ziff Davis, LLC. 28 E 28th Street New York, NY 10016
CWKorn  

achievements
 
View this online
Ask a new question
 
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language