Question from newbie_bc on Feb 16 at 8:05 PM Hello PP Gurus, I have a process that needs to be tested in development first but when I try to use the version LT and planning horizon is from 2014.02.11 to 2015.03.24 and planning period is M(month) , only 01.2015, 02.2015,03.2015 in table tab are available months for 2014 is not available. I tried using weeks and days for planning period but still the months for 2014 is not available... quality and production servers don't have any problem when using this tcode. I have checked the calendar setting using SCAL and they are the same... What do you think is the problem? How to solve this? | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |