Reply from snsapsd on Mar 26 at 6:29 AM Hi Saed, For cutover you require cutover strategy and plan, the stretegy should emphasis on what are the modules will have cutover data, its not necessary that all the modules should have cutover data, it depends upon the business requirement, you need to conduct a workshop with business along with stake holder to understand the business requirement and what data they prefer to carry from legacy system, for eg in MM module you can close the existing open Purchase order in legacy system and create new PO in SAP manually or you have to create a uploading template and upload open PO.
| | | ---------------Original Message--------------- From: melvin velez Sent: Tuesday, March 26, 2013 5:30 AM Subject: Cutover Strategy and Sequencing If you have not define these yet , you are not ready for cut over,I have no idea of the size of your project , but you are asking about legacy data , at this stage you should have all data mapping done and should have tested it . The data load sequence is as critical if not more than the migration itself . My advise if this is not well defined for all data objects and fully tested, STOP , you are heading for a total meltdown . Best regards Mel | | Reply to this email to post your response. __.____._ | In the Spotlight Become a blogger at Toolbox.com and share your expertise with the community. Start today. _.____.__ |