Reply from sop57 on Jun 4 at 2:00 PM Hi, If the lead time for the June demand takes the start date (release date of the req) back before 06/04/12 (I guess this is the 4th June) then the req will not have the vendor on it because the vendor was not valid then for the material. Change the start date on the source list to 01/01/12 and re-run MRP or use MD43, and the vendor will come throgh onto the June req. Regards, SOP57
| | | ---------------Original Message--------------- From: ganesan_p Sent: Monday, June 04, 2012 8:17 AM Subject: Vendor Flow in PR Hi Gurus, Created 3 month planning (June 100 EA, July 150 EA and Aug 200 EA) and Executed MRP, So totally 3 PR created, The Problem is June 100 EA PR itself only Vendor will not come automatically but other Two months PR itself Vendor will come automatically, Source List one Line item only available and its fixed Valid From 06/04/2012, Valid To 12/31/2012, Vendor 48180 Thanks & Regards, Ganesan, | | Reply to this email to post your response. __.____._ | _.____.__ |