Announcement:
wanna exchange links? contact me at sapchatroom@gmail.com.
Posted by
Admin at
Reply from sumandattsharma on Jun 27 at 3:06 AM Hi, In PR the price will come by valuation price from material master, but in PO it works by pricing procedure. If you maintain any info-record or contract the price flow from these condition records. Please explain your business scenario in brief. Why this setting is necessary for your business please elaborate. Thank you, Suman
| | | ---------------Original Message--------------- From: dawrul Sent: Wednesday, June 27, 2012 2:51 AM Subject: An Issue With a Unit Price in Conversion of PReq and PO When I convert my PReq to PO, an unit price in a line is not moving from first document to the other one. I need to fill out the price manually in PO again even it was done in PReq. Where is an option in SPRO for MM to fix this issue? Or can I fix it? I appreciate any help. | | Reply to this email to post your response. __.____._ | _.____.__ |