RE:[sap-log-mm] Packaging Lead Time Automation

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Reply from ha_tran on May 7 at 3:30 AM
Hi,

Since the planned delivery time was defined at either contract / purchasing info record or material master level, the workaround solution in this particular case, is to maintain 4 wks in the material master and 3 wks in the contract / purchasing info record (as you have already purchased from the vendor).

Cheers,
HT

---------------Original Message---------------
From: vijesh vijayan
Sent: Monday, May 07, 2012 1:26 AM
Subject: Packaging Lead Time Automation

Hi all,
In our scenario we are souring packing from suppliers. The lead time for the packaging is differs ,i.e., if it is new item the lead time is 4 weeks and for the old one the lead time is 3 weeks. For the new items we can update the lead time as 4 weeks once the item is received can system change it the lead time to 3 weeks automatically? Can SAP do it?
Please advise.
Regards,

 
Reply to this email to post your response.
 
__.____._
Manage Settings | Unsubscribe | Create FAQ | Send Feedback
  
Copyright © 2012 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ha_tran  
Senior SAP Supply Chain Business Analyst
achievements
 
Mark as helpful
View this online
Ask a new question
 
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements

_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language