Question from srini671 on Apr 9 at 5:42 PM Our client is not using Master reciepe or Resource. Instead they have only 1 default operations in Process Order. Our client Process Order Process is only relevant to Consumption of Raw Materials and Reciept of Finished Product. Our client does not have Auto GR setup and hence they have additional step of GR for finished goods after Production confirmation. We have the following Issue: When we try to settle a Process in K088. We get the message that there is a blance in order. Order cannot be settled. Can any one help us with possible causes? | Reply to this email to post your response. __.____._ | _.____.__ |