Reply from VidhyaDhar on Jan 8 at 9:56 PM Hi You could execute a report to list out assets with the incorrect cost center requiring a change. Create a worklist of the same and the system assigns a number to the worklist. Write a suitable substitution procedure to change the cost center and assign the same to your company code. Release the work list and your incorrect cost centers stand changed. Regards VidhyaDhar
| | | ---------------Original Message--------------- From: Nely Fernandez Sent: Sunday, January 08, 2012 9:50 PM Subject: Mass Change for Asset Cost Centre from Old to New Hi, From changing from old to new cost centers of various asset numbers, how to proceed doing mass changing asset cost centers instead of changing individual process? Thanks in advance. Nely | | Reply to this email to post your response. __.____._ | _.____.__ |