[sap-log-mm] MRP type PD, safety time

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Posted by edifi527
on Jun 16 at 2:13 AM
Hello everyone,

I have a question concerning MRP type PD (MRP). Does SAP consider delivery lead time when it releases a procurement proposal for material?

For example, lets say that you have a material with delivery lead time = 2 weeks and safety stock set to 0. You have released sales & planned orders for, say 9 weeks in the schedule with the first 3 weeks frozen, and SAP calculates that, with today's production plan, you will reach a zero stock level in 6 weeks. Does it release a procurement proposal TODAY or in week 4 (because the lead time is 2 weeks)? If the latter case is true, is there a way to set a safety time so that it releases a procurement proposal in, for example, week 3?

Best Regards,
Ed
__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
View this online
  
Popular White Papers

In the Spotlight
SAP Enterprise Mobility Webcast Watch today!
_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language