Posted by
Admin at
Hello, I am trying to use Quota Planning with PCP. I have set up a Quota Planning Cost Type that is 'Non CO Relevant' and attached to a Statistical Key figure. I marked it as 'non-cumulative' as the documentation states. I run Data Gathering for Orgs, with method Quota planning and the Cost Item I described above. SAP creates Infotype 5010 for the Org Unit I select. However, the number in the infotype is no the difference between the Planned and Current, it is the total of the Planned (i.e the Current is 2 and the Planned is 3 but SAP returns 3 when I was expecting 1). Can anyone help me with this? Thanks Alex | __.____._ Copyright © 2011 Toolbox.com and message author. Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251 | | Most Popular White Papers In the Spotlight _.____.__ |