RE:[sap-log-mm] Material price change in PO due to government control

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Posted by VIVEK MANE
on Jan 16 at 10:37 PM
Sir

The main problem is the change in material price itself which will be changing every month. How to account this. De-releasing PO every time is a big task. Also any change after GR is done will affect procurement and inventory report.

Regards

Vivek

---------------Original Message---------------
From: VIVEK MANE
Sent: Friday, January 14, 2011 1:09 AM
Subject: Material price change in PO due to government control

Hi

Our client has a business requirement as below.

Po has price variation clause wherein price will vary monthly.
The order has been placed on a approximate Base value provided by the vendor.
The deliveries would happen in multiple shipments and rates would vary each shipmentwise and monthwise.
This will continue in future.

What we want to suggest to them is to use Quantity contract with periodical release order as per actual price.

Also for current POs placed we want to ask them to check with finance if they can increase the Price and do the MIRO.

Require valuable opinion in this case.

Regards

vivek

__.____._
Copyright © 2011 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Mark as helpful
View this online
  
Most Popular White Papers

In the Spotlight
Toolbox.com Groups Discussions Now Support BBCode. Share Code Snippets with Peers
_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language