Posted by ha_tran (Senior SAP Supply Chain Business Analyst)
on Aug 24 at 7:10 PM
Mark this reply as helpfulMark as helpful
Hi,

If the PO is created with reference to PR, then the PR delivery date is defaulted into PO delivery date. If PO is created without reference to PR, then SAP will take into account the following parameters to determine the PO delivery date -

1) Planned delivery time. This can be from either material master or purchasing master data record such as contract or info record; and
2) GR processing time. This can be defaulted from the material master

If the values of these parameters set as ZERO, then the delivery date of the PO will be defaulted as today's day (i.e the day the PO is created). If the PO delivery date is blanked out automatically, then you shall check if there is any BAdI that was activated to blank it out automatically (after the above-mentioned default is made).

Cheers,
HT

---------------Original Message---------------
From: MM
Sent: Tuesday, August 24, 2010 5:25 AM
Subject: Delivery date in PO

> Hi Experts
>
> When I'm creating a purchase order, the delivery date for the articles are populated automatically . However for one particular plant, the delivery date is not populated.
>
> Please send your suggestions to solve why this does not work for one particular plant ?
>
> Regards
>
> MM

__.____._
Copyright © 2010 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ha_tran
SAP Logistics Material Management Helper

Posted helpful replies on 50 threads in a group to earn a Silver Achievement
_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language