RE:[sap-log-mm] Why Does MRP Ignore Matl Master Planned Delivery Time when Creating Req [ROP] when I add a source list?

Posted by Admin at
Share this post:
Ma.gnolia DiggIt! Del.icio.us Yahoo Furl Technorati Reddit

Posted by stuart lowe
on Jul 8 at 6:25 PM
Mark this reply as helpfulMark as helpful
Check your config in OMDT. Here you determine if the material master or the info record / contract determines the lead time.

---------------Original Message---------------
From: kurtstep
Sent: Thursday, July 08, 2010 10:06 AM
Subject: Why Does MRP Ignore Matl Master Planned Delivery Time when Creating Req [ROP] when I add a source list?

> Hello experts:
>
> Quick question - we are attempting to use source lists to automatically assign purchase req to correct vendor and GOA. We noticed that when we add source list - that MRP generated purchase requisitions default the delivery date to tomorrow - and ignore the lead time associated with plant, material number in material master.
>
> When I delete the source list - and close req, then rerun MRP for the plant and material to generate a new Req - the delivery date on req is correctly calculated [considers planned delivery time].
>
> Is there additional info that I need to set up to have req created with correct delivery date? [we have an info record created that has been marked for deletion]
>
> Thanks - KurtS

__.____._
Copyright © 2010 Toolbox.com and message author.

Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
In the Spotlight
Earn Recognition for Your Contributions at Toolbox for IT. Gain Points for Community Achievements
_.____.__

0 comments:

Post a Comment

T r a n s l a t e to your language