RE:[sap-log-mm] how to manage roll material like a film??
Posted by
Admin at
Share this post:
|
0 Comments
Posted by ha_tran (Senior SAP Supply Chain Business Analyst) on May 1 at 11:18 PM | Mark as helpful |
Hi,
If the length varies every time the GR is posted and if it is the meter unit of measure that will be used in reservation as well as goods issue transactions, then it is logical that meter shall be defined as base unit of measure / stock keeping unit.
Cheers,
HT
---------------Original Message---------------
From: channylove
Sent: Thursday, April 29, 2010 7:47 PM
Subject: how to manage roll material like a film??
> hello~~ guys~~
>
> I'm doing a SAP project.
>
> I have some problem now.
>
> we are using roll type material as raw material with batch management.
>
> but, everytime the unit are different.
>
> today we receipt 1 roll, 1200 meter with batch no 100.
>
> yesterday, we receipt 1 roll, 1100 meter with batch no 99.
>
> two material have same material code.
>
> When we issue these material, we must issue by roll not meter unit.
>
> In that case, who make material issue reservation are doesn't know what batch has specific meter.
>
> even if user make reservation that has material 1000meters, we need to issue 1100 meters, batch 99.
>
> how can i set up IMG??
__.____._ If the length varies every time the GR is posted and if it is the meter unit of measure that will be used in reservation as well as goods issue transactions, then it is logical that meter shall be defined as base unit of measure / stock keeping unit.
Cheers,
HT
---------------Original Message---------------
From: channylove
Sent: Thursday, April 29, 2010 7:47 PM
Subject: how to manage roll material like a film??
> hello~~ guys~~
>
> I'm doing a SAP project.
>
> I have some problem now.
>
> we are using roll type material as raw material with batch management.
>
> but, everytime the unit are different.
>
> today we receipt 1 roll, 1200 meter with batch no 100.
>
> yesterday, we receipt 1 roll, 1100 meter with batch no 99.
>
> two material have same material code.
>
> When we issue these material, we must issue by roll not meter unit.
>
> In that case, who make material issue reservation are doesn't know what batch has specific meter.
>
> even if user make reservation that has material 1000meters, we need to issue 1100 meters, batch 99.
>
> how can i set up IMG??
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ha_tran
SAP Logistics Material Management Enthusiast
Contributed 500 posts in a group to earn a Silver Achievement
SAP Logistics Material Management Enthusiast
Contributed 500 posts in a group to earn a Silver Achievement
Related Content
In the Spotlight
_.____.__ White Papers
In the Spotlight
Toolbox.com for iPhone: Ask Questions & Get Answers Anywhere. Use the New iPhone App