Re: [sap-log-mm] Components do Not Reverse - Sub-Contracting PO
Posted by
Admin at
Share this post:
|
0 Comments
Posted by Denise Michaels on May 2 at 7:38 PM | Mark as helpful |
Have you verified that the stock is not back in vendor stock (try transaction MBLB). The consumption is from vendor stock which is not in a storage location.
The reversal not happening could be due to missing authorization for the 544 movement, or to missing finance config for that movement.
Suggest that you initiate a reversal movement in MIGO, and perform the "check" function to see what messages are generated.
From: Sap MM module via sap-log-mm <sap-log-mm@Groups.ITtoolbox.com>
To: Denise Michaels <deniseemichaels@yahoo.com>
Sent: Sat, May 1, 2010 9:24:10 PM
Subject: RE:[sap-log-mm] Components do Not Reverse - Sub-Contracting PO
Posted by Sap MM module (SAP MM Functional)
on May 2 at 12:27 AM Mark as helpful
Hi
The GR was revesred by the 102 mvt from MIGO.
The BOM header was the GRIN & the ROMA is the components.
While reveresing the GR GRIN material get revesred but the ROMA components material is not coming in the Stock.
the Important point :
After hitting the GR for GRIN material in the System get cleared in QM module UD (Quality to unrest). But when the GR is reversed the ROMA components material is not coming in the Stock.
Thank you
With Best Regards
Rohan Trimbakkar
---------------Original Message---------------
From: ha_tran
Sent: Monday, April 26, 2010 1:43 AM
Subject: Components do Not Reverse - Sub-Contracting PO
> Hi Rohan,
>
> Can you rephrase your inquiry?. What is the BOM header material ID? and BOM component material ID? Was ROMA the material ID of both BOM header and BOM component? How was your GR cancelled? Was it done via MBST transaction?
>
> Cheers,
> HT
__.____._ The reversal not happening could be due to missing authorization for the 544 movement, or to missing finance config for that movement.
Suggest that you initiate a reversal movement in MIGO, and perform the "check" function to see what messages are generated.
From: Sap MM module via sap-log-mm <sap-log-mm@Groups.ITtoolbox.com>
To: Denise Michaels <deniseemichaels@yahoo.com>
Sent: Sat, May 1, 2010 9:24:10 PM
Subject: RE:[sap-log-mm] Components do Not Reverse - Sub-Contracting PO
Posted by Sap MM module (SAP MM Functional)
on May 2 at 12:27 AM Mark as helpful
Hi
The GR was revesred by the 102 mvt from MIGO.
The BOM header was the GRIN & the ROMA is the components.
While reveresing the GR GRIN material get revesred but the ROMA components material is not coming in the Stock.
the Important point :
After hitting the GR for GRIN material in the System get cleared in QM module UD (Quality to unrest). But when the GR is reversed the ROMA components material is not coming in the Stock.
Thank you
With Best Regards
Rohan Trimbakkar
---------------Original Message---------------
From: ha_tran
Sent: Monday, April 26, 2010 1:43 AM
Subject: Components do Not Reverse - Sub-Contracting PO
> Hi Rohan,
>
> Can you rephrase your inquiry?. What is the BOM header material ID? and BOM component material ID? Was ROMA the material ID of both BOM header and BOM component? How was your GR cancelled? Was it done via MBST transaction?
>
> Cheers,
> HT
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Denise Michaels
SAP Logistics Material Management Enthusiast
Contributed 100 posts in a group to earn a Bronze Achievement
SAP Logistics Material Management Enthusiast
Contributed 100 posts in a group to earn a Bronze Achievement
In the Spotlight
_.____.__ Toolbox.com for iPhone: Ask Questions & Get Answers Anywhere. Use the New iPhone App