Posted by ha_tran (Senior SAP Supply Chain Business Analyst) on Mar 28 at 5:13 PM | Mark as helpful |
Hi GT,
Yes, it is of standard functionality of SAP that the planned delivery time in info record document is not taken into account during manual creation of either PR or PO (with or without reference to PR). However, SAP does provide the standard feature to consider the planned delivery time during MRP run to generate PR if the setting in OMI8 transaction is made for your related plant and the info record vendor is maintained in the source list with ''1'' MRP-relevant indicator.
Cheers,
HT
---------------Original Message---------------
From: GT
Sent: Sunday, March 28, 2010 2:13 PM
Subject: Delivery date in PR and PO
> Hi,
>
> Background:
> - We are maintaining Planned delivery time in Purchasing info records, while we have not maintained any settings for PO processing time nor GR processing time. We are running on ECC 6.0 and have not done any enhancements / changes to this area.
>
> - We are raising both PR's and PO's (with/without reference to PR) manually.
>
> - When raising PR's manually (ME51N) system is always proposing current day as the delivery date, not taking the planned delivery time from the PIR into consideration.
>
> - System behaves exactly same way when raising PO's manually (ME21N) (with/without reference to PR), i.e. always proposing current day as delivery date, not taking the planned delivery from the PIR into consideration.
>
> Question:
> (1) Is the above behavior for setting delivery date equal to current day in the PR (and not taking the planned delivery time from the PIR) as per standard SAP when creating PR's manually? If not, any idea what the problem might be?
>
> (2) Is the above behavior for setting delivery date equal to current day in the PO (and not taking the planned delivery time from the PIR) as per standard SAP when creating PO's manually? If not, any idea what the problem might be?
>
> Thanks in advance.
>
> Regards, GT
__.____._ Yes, it is of standard functionality of SAP that the planned delivery time in info record document is not taken into account during manual creation of either PR or PO (with or without reference to PR). However, SAP does provide the standard feature to consider the planned delivery time during MRP run to generate PR if the setting in OMI8 transaction is made for your related plant and the info record vendor is maintained in the source list with ''1'' MRP-relevant indicator.
Cheers,
HT
---------------Original Message---------------
From: GT
Sent: Sunday, March 28, 2010 2:13 PM
Subject: Delivery date in PR and PO
> Hi,
>
> Background:
> - We are maintaining Planned delivery time in Purchasing info records, while we have not maintained any settings for PO processing time nor GR processing time. We are running on ECC 6.0 and have not done any enhancements / changes to this area.
>
> - We are raising both PR's and PO's (with/without reference to PR) manually.
>
> - When raising PR's manually (ME51N) system is always proposing current day as the delivery date, not taking the planned delivery time from the PIR into consideration.
>
> - System behaves exactly same way when raising PO's manually (ME21N) (with/without reference to PR), i.e. always proposing current day as delivery date, not taking the planned delivery from the PIR into consideration.
>
> Question:
> (1) Is the above behavior for setting delivery date equal to current day in the PR (and not taking the planned delivery time from the PIR) as per standard SAP when creating PR's manually? If not, any idea what the problem might be?
>
> (2) Is the above behavior for setting delivery date equal to current day in the PO (and not taking the planned delivery time from the PIR) as per standard SAP when creating PO's manually? If not, any idea what the problem might be?
>
> Thanks in advance.
>
> Regards, GT
Copyright © 2010 Toolbox.com and message author.
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
Toolbox.com 4343 N. Scottsdale Road Suite 280, Scottsdale, AZ 85251
ha_tran
SAP Logistics Material Management Helper
Posted helpful replies on 5 threads in a group to earn a Bronze Achievement
SAP Logistics Material Management Helper
Posted helpful replies on 5 threads in a group to earn a Bronze Achievement
In the Spotlight
_.____.__ 55% of IT Pros Use Social Media to Advance Their Careers. See the Survey Results